Following the on-season construction of Nemesis Inferno in 2002, from preparation to track being complete.
April 9th 2002 - The work starts here on the footers and on the station wall.
August 9th 2002 - Track Arrives at the park, station and first drop starts to go up.
August 22nd 2002 - Track Installed with the first drop and tunnel complete.
August 29th 2002 - loads of new supports going up.
September 27th, Lift, drop, loop and Inline up since last update. Structure also starting to take shape.